Europe • Latest News • Wastewater • Water Treatment

Barhale wins £11.4m Severn Trent contract to upgrade Milton wastewater works in Derbyshire

Circular trickling filter beds on green grass beside brick buildings, with a large electricity pylon under a clear blue sky
  • Severn Trent Water has awarded Barhale an £11.4m contract to upgrade Milton Wastewater Treatment Works in south Derbyshire.
  • The works, east of Burton-on-Trent, will gain 50% more hydraulic and treatment capacity to serve a projected population equivalent of 30,000.
  • A new 17m-diameter stainless steel storm tank will add 1,135m³ of capacity, taking total storm storage to 1,782m³.
  • New inlet works will be manufactured off site by EPS Water, and the treatment works will remain fully operational during construction.
  • Work is expected to be completed in the third quarter of 2027.

Severn Trent Water has awarded Barhale an £11.4m contract to upgrade Milton Wastewater Treatment Works (WwTW) in south Derbyshire. The scheme is intended to accommodate projected population growth in the area served by the site, which lies east of Burton-on-Trent.

Barhale is a civil engineering, infrastructure and tunnelling specialist that was established as a tunnelling contractor in 1980. The work at Milton involves major civil, mechanical and electrical improvements and is due to be completed in the third quarter of 2027.

Capacity increase at Milton Wastewater Treatment Works

Barhale will increase the hydraulic and treatment capacity of the works by 50%. This will allow the site to serve a projected population equivalent of 30,000 while maintaining its existing final-effluent standards. Population equivalent is a standard measure used to express the treatment load a works must handle.

The project will also improve the facility’s resilience to storm flows. Channels, pipework, chambers and manholes across the site will be upgraded to accommodate the increased flows and driving head.

Early contractor involvement and off-site manufacture

The detailed design was developed through an extensive early contractor involvement phase. During this phase, Barhale worked with its in-house designer, ESL, and with Severn Trent Water.

Barhale will install new high-level inlet works incorporating screening, grit removal, flow measurement and flow separation. The equipment will be manufactured off site by water technology provider EPS Water and then connected to an existing balancing tank and downstream assets.

New storm tank and process upgrades

A new above-ground stainless steel storm tank, 17m in diameter and 5m high, will provide an additional 1,135m³ of capacity. This will bring the total storm-storage volume at the works to 1,782m³, an overall increase of approximately 500m³.

The primary settlement tanks will be fitted with new desludge pumps. Hydraulic modifications will be made to the raising weirs, diffuser drums and skimmer blades, and the outlet pipework will be replaced.

The existing spill tanks will be demolished to make way for a new in-ground humus settlement tank. Barhale will also modify the existing dry wells and convert the works return wet well into a dry well. New control panels will be installed and integrated with the existing motor control centres.

Keeping a live works operational

All the improvements will be delivered while the treatment works remains fully operational. Sean McCormick, contracts manager at Barhale, said: “Milton is a significant upgrade of a live treatment works, so maintaining performance throughout construction has been central to the design.”

He added: “Our early collaboration with Severn Trent, our in-house designer ESL and other delivery partners has allowed us to plan the new assets around the existing treatment process and maximise off-site manufacture. We will continue to work closely with Severn Trent’s operations team to bring the additional capacity into service with minimal disruption to the live works.”

Nick Moczadlo, project manager at Severn Trent, said: “It’s great to partner with Barhale on these important improvements at our Milton Waste Treatment Works. Through the early collaboration, we have been able to set out a plan that will help the site keep up with growing demands through population growth, as well as keep the site running to avoid any loss of operational activity.”

Wider Severn Trent and Barhale work

The Milton contract follows other collaboration between the two companies. H2O Global News has previously reported on how Severn Trent and Barhale cut £2m from the Ravenstone wastewater upgrade in Leicestershire by retaining and optimising existing infrastructure.

Once complete, the upgrade is expected to give Milton Wastewater Treatment Works the capacity to meet the projected growth in demand in south Derbyshire.

Frequently asked questions

Who is upgrading Milton Wastewater Treatment Works?

Severn Trent Water has awarded the £11.4m contract to Barhale, a civil engineering, infrastructure and tunnelling specialist. The detailed design was developed with Barhale’s in-house designer, ESL.

Where is Milton Wastewater Treatment Works?

The works is in south Derbyshire, east of Burton-on-Trent.

How much will the Milton upgrade increase capacity?

Hydraulic and treatment capacity will rise by 50%, allowing the works to serve a projected population equivalent of 30,000. A new storm tank will take total storm storage to 1,782m³.

Will the treatment works keep operating during construction?

Yes. The works will remain fully operational while the civil, mechanical and electrical improvements are carried out.

When will the Milton WwTW upgrade be completed?

Work is expected to be completed in the third quarter of 2027.